DC1000T / Procurement specification 10-01

1000 Ton Aluminum Cold Chamber Die Casting Machine

The DC1000T is a 10,000 kN cold chamber platform for large aluminum and magnesium projects. Treat it as a complete capital-equipment package: approve the machine only after clamp demand, complete shot, die interfaces, process window, automation, factory services, delivery, and acceptance evidence agree in one controlled technical specification.

Published DC1000T data reviewed August 10, 2026 by Cathy, Director. Approved project drawings and the signed technical agreement govern the final supply.

REFERENCE VISUAL / DC1000TDC1000T 1000 ton aluminum cold chamber die casting machine procurement visualization with English model marking
Procurement visualization based on a published heavy cold chamber machine reference. Confirm the final geometry, colors, guarding, controls, hydraulic components, shot end, options, and complete supply boundary in approved documents.
Clamping force10,000 kN
Tie-bar opening1,030 x 1,030 mm
Die thickness450-1,150 mm
Aluminum shot10-18 kg
Approx. weight70 t

Capital approval memo

The direct answer: tonnage starts the review; it does not finish it

The DC1000T belongs on the shortlist only when one traceable engineering file clears six independent boundaries. Purchasing can then compare quotations against the same approved assumptions instead of comparing incomplete base-machine prices.

  1. 01

    Clamping calculation

    Record total pressure-exposed projected area, cavity-pressure basis, alloy, slide effects, quality risk, and operating margin. The result must stay within 10,000 kN.

    Owner: process engineering
  2. 02

    Complete shot and pressure

    Include castings, runners, biscuit, overflows, and allowance. Select one plunger only when both metal capacity and required intensification pressure pass.

    Owner: process + supplier
  3. 03

    Die and movement envelope

    Verify die width, height, 450-1,150 mm thickness, weight, mounting, opening, ejection, slides, cooling, vacuum, lifting, and changeover route.

    Owner: tooling engineering
  4. 04

    Cell interfaces

    Freeze furnace, dosing, spray, extraction, trim, conveyors, inspection, scrap, guarding, I/O, recipes, traceability, and recovery sequences.

    Owner: automation integrator
  5. 05

    Factory readiness

    Approve access, lifting, floor and foundation, electrical supply, cooling water, air, exhaust, oil-temperature control, service zones, and local safety rules.

    Owner: plant engineering
  6. 06

    Acceptance and lifecycle

    Define FAT, SAT, sample conditions, measurement methods, pass criteria, documents, training, backups, spares, warranty, and response obligations.

    Owner: quality + purchasing

Schedule B / Shot-end selection

Four packages create four different pressure-capacity windows

The largest plunger is not automatically the safest option. A larger diameter increases the published metal allowance while reducing intensification pressure. Screen the actual complete shot and process-pressure requirement together, then lock the sleeve, plunger, injection position, flange, cooling, lubrication, and spare set into the technical agreement.

PackageAluminumMagnesiumPressureCasting areaProcurement note
SP-190 mm10.0 kg7.2 kg126 MPa790 cm2

Highest published intensification pressure and the lowest complete-shot allowance.

SP-2100 mm12.5 kg9.0 kg102 MPa980 cm2

Higher pressure option with more metal allowance than the 90 mm package.

SP-3110 mm15.0 kg10.8 kg84 MPa1,190 cm2

Capacity-led middle option; verify the reduced pressure against the process requirement.

SP-4120 mm18.0 kg12.9 kg71 MPa1,390 cm2

Largest published shot allowance and the lowest listed intensification pressure.

Schedule C / Published model data

DC1000T technical specifications

Use these values for initial screening and RFQ normalization. Require approved datums, tolerances, interface drawings, component schedules, utility data, and installation drawings before technical release.

C1

Clamp, platen, and die

Clamping force
10,000 kN
Clamping stroke
800 mm
Ejecting force
500 kN
Ejection stroke
200 mm
Die thickness range
450-1,150 mm
Platen size
1,620 x 1,620 mm
Tie-bar diameter
200 mm
Tie-bar spacing
1,030 x 1,030 mm
C2

Injection and shot end

Injection force
805 kN
Injection stroke
850 mm
Plunger diameters
90 / 100 / 110 / 120 mm
Aluminum shot weights
10 / 12.5 / 15 / 18 kg
Magnesium shot weights
7.2 / 9 / 10.8 / 12.9 kg
Intensification pressure
126 / 102 / 84 / 71 MPa
Published casting area
790-1,390 cm2
Maximum casting area
2,500 cm2
Injection positions
-100 / -300 mm*
Plunger launch distance
300 mm
Shot-chamber flange
240 mm diameter
Flange protrusion
20 mm
C3

Power and installation

Motor power
45 kW
System pressure
16 MPa
Oil tank capacity
1,500 L
Approx. machine weight
70 t
Approx. machine size
10 x 3.3 x 3.7 m
Listed materials
Aluminum / magnesium
Published slow-shot range
0.1-1.4 m/s
Published max. air-shot speed
At least 7 m/s

Source: current manufacturer-published DC1000T product data, reviewed August 10, 2026 by Cathy, Director | *Confirm injection-position datums and usable positions on the project drawing | Final signed technical agreement takes precedence.

Published manufacturer reference: ShiMi DC1000T Standard Cold Chamber Die Casting Machine. Use this public record to cross-check the web summary; approved supplier drawings and the signed technical agreement govern the final configuration.

Schedule D / System evidence

Turn close-up images into maintainability questions

These references have been cleaned of Chinese and brand text. They indicate component families and service areas; they do not guarantee that every visible make, quantity, arrangement, or color is included in a quotation.

D1 / REVIEW ZONELarge cold chamber die casting machine hydraulic manifold, pumps, hoses, fittings, and service zone without Chinese labels

Hydraulic distribution and service interface

Use this reference to agree component makes, circuit ownership, filtration, oil specification, cooling duty, hose and seal spares, diagnostic points, safe isolation, access zones, and the maintenance documentation supplied with the machine.

D2 / REVIEW ZONECold chamber die casting machine pressure-control valve block, gauge, solenoids, wiring, and fittings without Chinese labels

Pressure regulation and response verification

The technical agreement should identify calibration points, pressure and speed verification, accumulator discharge procedure, repeatability evidence, alarm tests, replacement parts, and the exact acceptance method used during FAT and SAT.

Schedule E / Site and logistics

A 70 ton machine is a building project as well as an equipment purchase

The published 10 x 3.3 x 3.7 m envelope covers the base machine, not the complete cell. Peripherals, platforms, guarding, piping, maintenance access, die handling, and hot-metal safety zones expand the installed footprint.

70 tpublished machine weight
before cell peripherals
E1

Transport and lifting

Confirm shipping split, packed dimensions and weights, center of gravity, lifting points, port and inland restrictions, unloading equipment, crane capacity, hook height, rigging plan, doorway and aisle clearances, floor transitions, and positioning responsibility.

E2

Foundation and access

Approve floor loading, pits, anchoring, leveling, grout, drainage, oil containment, vibration considerations, die-change route, crane coverage, platen and tie-bar service, accumulator access, panel clearance, and safe escape paths from final drawings.

E3

Utilities and thermal duty

State voltage, frequency, transformer and cable boundary, connected and operating demand, cooling-water flow and quality, compressed air, oil-temperature control, furnace energy, exhaust, network, every point of supply, and responsibility for local distribution.

E4

Safety and compliance

Define applicable standards, risk-assessment ownership, guarding and interlocks, emergency zones, platforms, stairs, lockout points, hot-metal hazards, labels and language, operator visibility, validation records, environmental obligations, and site permits.

Schedule F / Responsibility matrix

Normalize every quotation before comparing price

Ask each supplier to answer the same line items with Included, Optional, By Buyer, or Excluded, plus a technical reference and price effect. This exposes interface gaps early and keeps the commercial comparison tied to an executable project.

F1

Base machine and selected shot end

Controls, hydraulics, lubrication, core pulls, cooling interfaces, guarding, die protection, selected sleeve and plunger, injection positions, options, component makes, coatings, oil charge, and every exclusion.

F2

Automation and process equipment

Furnace, dosing, spray, extraction, quench, trim, conveyors, scrap, marking, inspection, vacuum, thermal control, grippers, fixtures, safety integration, recipes, I/O, data, and cycle ownership.

F3

Delivery and site services

Incoterm, packing, insurance, shipment, unloading, positioning, foundation information, piping, cabling, installation, commissioning, sample material, production support, local labor, permits, and utilities.

F4

Evidence and lifecycle support

Drawings, manuals, certificates, risk files, software and backups, FAT and SAT records, training, translated documents, included and recommended spares, warranty start, remote support, service response, and escalation route.

Acceptance rule

Define the casting, die, alloy, sample quantity, cycle basis, quality checks, measuring equipment, machine settings, environmental conditions, repeatability evidence, capability requirement, pass criteria, open-action process, retest rules, and who pays when prerequisites are missing.

Schedule G / Buyer FAQ

Questions to close before technical and commercial approval

Use these direct answers for early screening. Put the project-specific calculations, drawings, tolerances, owners, test conditions, and evidence into the signed agreement.

G1What is the DC1000T aluminum die casting machine best suited for?

The DC1000T is an initial candidate for large aluminum or magnesium projects whose verified clamp demand, complete shot, die envelope, required process pressure, automation, and factory interfaces fit the published 10,000 kN platform and one confirmed 90, 100, 110, or 120 mm shot package. Nominal tonnage alone does not approve a part.

G2What are the main DC1000T technical specifications?

Published data lists 10,000 kN clamping force, 800 mm clamping stroke, 500 kN ejecting force, 200 mm ejection stroke, 450-1,150 mm die thickness, 1,620 x 1,620 mm platens, 1,030 x 1,030 mm tie-bar spacing, 805 kN injection force, 850 mm injection stroke, a 45 kW motor, 1,500 L oil tank, and approximate 70 ton machine weight.

G3How should the 90, 100, 110, or 120 mm shot package be selected?

Check complete shot and required intensification pressure together. Published aluminum allowances rise from 10 to 18 kg as plunger diameter increases, while listed intensification pressure falls from 126 to 71 MPa. Select the smallest package that clears complete shot while preserving the documented pressure window and process margin.

G4How do I check whether 10,000 kN clamping force is enough?

Total the projected area of every cavity, runner, overflow, biscuit influence, and pressure-exposed slide, multiply by the agreed cavity-pressure assumption, then apply the documented operating margin. Check the result against 10,000 kN separately from the shot package, die fit, and the published 2,500 cm2 maximum casting area.

G5What site work should be completed before a DC1000T order?

Approve the transport route, unloading and lifting plan, foundation and anchoring, 70 ton machine load, 10 x 3.3 x 3.7 m bare-machine envelope, die-change route, service clearances, electrical supply, cooling water, compressed air, exhaust, oil-temperature control, safety standard, and all peripheral footprints from final drawings.

G6What should the DC1000T quotation, FAT, and SAT documents include?

Require a line-by-line supply boundary, selected shot end, controls and hydraulic makes, core pulls, cooling and vacuum interfaces, furnace and automation ownership, utilities, guarding, drawings, manuals, backups, spares, packing, commissioning, training, warranty, and exclusions. FAT and SAT should define test conditions, measurements, records, pass criteria, open-action ownership, and retest rules.

DC1000T controlled inquiry

Send one project dossier for one accountable response

A useful proposal should return a stated model-fit decision, selected shot package, interface register, preliminary cell layout, acceptance path, commercial boundary, and list of unresolved assumptions.

  1. 01

    Casting and process Alloy, drawings, projected area, cavity-pressure basis, cavities, net weight, runners, biscuit, overflows, complete shot, fill, quality, inspection, and traceability.

  2. 02

    Die and movement Size, thickness, weight, mounting, opening, ejection, slides, core pulls, cooling, vacuum, lifting, storage, and changeover method.

  3. 03

    Cell and performance Cycle, annual volume, shifts, OEE basis, furnace, dosing, spray, extraction, quench, trim, inspection, scrap, guarding, data, and recovery.

  4. 04

    Factory and delivery Layout, route, floor, crane, utilities, safety standard, destination, Incoterm, FAT, SAT, documents, installation, training, warranty, and spares.

Get a Quote WhatsApp