STANDARD COLD CHAMBER / DC300TDC300T 300 ton aluminum cold chamber die casting machine with yellow enclosure and no Chinese product text
Cleaned DC300T configuration reference based on the published machine image. Confirm controls, hydraulic components, automation, guarding, and every included option in writing.

DC300T / Production-cell planning platform

300 Ton Aluminum Cold Chamber Die Casting Machine

The DC300T combines a listed 3,000 kN clamp with three shot-end choices for aluminum and magnesium work. Approve it only after the projected area, complete shot, die envelope, required pressure, automation, utilities, and acceptance scope have been reviewed as one production system.

Published DC300T data reviewed August 9, 2026 by Cathy, Director. Final signed technical documents take precedence.

Clamping force3,000 kN
Die thickness250-700 mm
Tie-bar spacing580 x 580 mm
Al shot packages1.57 / 2.2 / 3.0 kg
Approx. weight11.5 t

Start with the production mission

Is the DC300T the right machine, not simply the next size?

The model is a defensible shortlist only when five independent checks pass. Do not use aluminum part weight as a substitute for projected area, die geometry, or process pressure.

Short answer

Consider the DC300T when the calculated clamp demand stays within 3,000 kN with the agreed margin, the complete metal demand fits one pressure-capacity package, the die clears the 580 x 580 mm opening and 250-700 mm thickness range, and the required cell interfaces can be documented.

  1. 01

    Clamp demand

    Total every pressure-exposed projected area, including runners, overflows, and applicable slides. State the cavity-pressure assumption and margin.

  2. 02

    Complete shot

    Include all cavities, runners, biscuit, overflows, and process allowance. Check aluminum or magnesium mass against the selected plunger package.

  3. 03

    Die and movement

    Verify width, height, thickness, weight, opening, mounting, ejection, core pulls, lifting route, cooling, and maintenance access.

  4. 04

    Process window

    Match fill profile, intensification pressure, plunger, shot sleeve, injection position, thermal control, vacuum, and quality target.

  5. 05

    Cell and factory

    Define furnace, ladler, sprayer, extractor, trimming, conveyors, guarding, utilities, floor plan, safety, documentation, and service boundary.

Pressure-capacity tradeoff

Three DC300T shot packages, three different process windows

The published packages link plunger diameter, metal capacity, intensification pressure, and casting area. Select the smallest package that satisfies the complete shot and required pressure with an agreed process margin.

PackageAluminumMagnesiumPressureCasting areaSelection note
0150 mm
1.57 kg1.10 kg162 MPa182 cm²

Highest listed pressure; lowest metal capacity.

0260 mm
2.20 kg1.57 kg113 MPa262 cm²

Middle package for balanced capacity and pressure.

0370 mm
3.00 kg2.00 kg83 MPa358 cm²

Highest listed shot capacity; lowest listed pressure.

Do not confuse maximum casting area with automatic approval: the published maximum is 780 cm². Actual allowable projected area depends on cavity pressure, geometry, alloy, quality requirement, and the operating margin accepted for the project.

Engineering data ledger

DC300T technical specifications

These values support initial comparison and RFQ preparation. Confirm dimensions, datums, component makes, interfaces, options, and tolerances in the quotation and approved drawings.

A

Clamp, platen, and die

Clamping force
3,000 kN
Clamping stroke
460 mm
Ejecting force
220 kN
Ejection stroke
105 mm
Die thickness range
250-700 mm
Platen size
900 x 900 mm
Tie-bar diameter
110 mm
Tie-bar spacing
580 x 580 mm
B

Injection and shot end

Injection force
370 kN
Injection stroke
430 mm
Plunger diameters
50 / 60 / 70 mm
Aluminum shot weights
1.57 / 2.20 / 3.00 kg
Magnesium shot weights
1.10 / 1.57 / 2.00 kg
Intensification pressure
162 / 113 / 83 MPa
Published casting area
182 / 262 / 358 cm²
Maximum casting area
780 cm²
Injection position
0-160 mm*
Plunger launch distance
150 mm
Shot-chamber flange
110 mm diameter
Flange protrusion
10 mm
C

Hydraulic power and installation

Motor power
22 kW
System working pressure
14 MPa
Oil tank capacity
800 L
Approx. machine weight
11.5 t
Approx. machine size
6.4 x 1.5 x 2.7 m
Listed materials
Aluminum / magnesium
Published slow-shot range
0.1-1.4 m/s
Published max. air-shot speed
≥ 8.5 m/s

Technical reference: current published DC300T product data, reviewed August 9, 2026 by Cathy, Director | *Confirm the injection-position datum and usable range in the project drawing | Final signed technical agreement takes precedence.

Published manufacturer reference: ShiMi DC300T Standard Cold Chamber Die Casting Machine. Use this public record to cross-check the web summary; approved supplier drawings and the signed technical agreement govern the final configuration.

Machine-zone review

Use the visible machine areas to write better RFQ questions

These are crops from the cleaned DC300T configuration reference, not separate machines. They help teams discuss interfaces and access without implying that every shown component is included.

ZONE 01DC300T yellow clamping enclosure, control station, and orange automatic extraction interface without Chinese text

Clamping enclosure and automatic extraction interface

Confirm platen access, die-change clearance, moving and fixed-side services, extractor or robot interface, guarding boundary, maintenance doors, and the sequence included in the control program.

ZONE 02DC300T injection cylinder, shot-end support, accumulators, gauges, and hydraulic service area without Chinese text

Injection unit, accumulators, and shot-end service zone

Specify the plunger and shot-sleeve package, injection positions, accumulator inspection method, pressure gauges, hydraulic brands, safe discharge procedure, service clearance, and recommended critical spares.

Complete cell boundary

The base machine is only one line in the investment

A comparable quotation must define molten-metal handling, die services, automation, downstream equipment, safety, utilities, documentation, and commissioning responsibilities around the DC300T.

Read the machine RFQ checklist ->
01 / METAL

Furnace and dosing

Holding or melting capacity, energy source, temperature control, ladler or dosing method, transfer height, metal-loss assumptions, and safety interfaces.

02 / DIE

Thermal and motion services

Cooling circuits, die-temperature control, vacuum, spray, core pulls, ejector interface, die clamps, lifting, changeover method, and leak testing.

03 / HANDLING

Extraction and finishing

Robot or extractor reach, gripper, part confirmation, conveyor, quench, trim press, scrap handling, marking, inspection, and reject routing.

04 / PLANT

Utilities and compliance

Voltage and frequency, cooling water, compressed air, exhaust, floor load, access route, guarding, safety standard, language, manuals, and training.

Factory acceptance plan

Turn machine claims into observable evidence

A useful FAT is agreed before shipment and records what was checked, by whom, with which instruments, limits, files, and corrective-action rules.

SAFETY

Interlocks, emergency stops, guards, pressure release, alarms, access, labels, and electrical protection.

MOTION

Dry-cycle sequence, clamping and opening stages, low-pressure die protection, ejection, lubrication, and core-pull logic.

INJECTION

Slow and fast stages, pressure build, repeatability evidence, selected shot package, positions, recipes, and trace data.

INTERFACES

Automation I/O, furnace and ladler signals, sprayer and extractor sequence, utilities, data access, and fault recovery.

DOCUMENTS

Approved drawings, electrical and hydraulic diagrams, parts list, manuals, certificates, backups, and spare-parts schedule.

DELIVERY

Included equipment, loose items, preservation, packing, lifting points, installation duties, commissioning, training, and exclusions.

DC300T procurement FAQ

Answers for model screening, quotation, and acceptance

Use these answers to align purchasing, process, tooling, maintenance, and plant teams before the technical agreement is signed.

Q01What is the DC300T aluminum die casting machine best suited for?

The DC300T is an initial candidate for aluminum or magnesium projects whose total projected-area calculation, complete metal demand, die envelope, and process pressure fit the listed 3,000 kN clamp and a confirmed 50, 60, or 70 mm plunger package. It should be selected from the actual casting and die data rather than the 300 ton label alone.

Q02What are the main DC300T technical specifications?

Current published data lists 3,000 kN clamping force, 460 mm clamping stroke, 220 kN ejecting force, 105 mm ejection stroke, 250-700 mm die thickness, 900 x 900 mm platens, 580 x 580 mm tie-bar spacing, 370 kN injection force, 430 mm injection stroke, a 22 kW motor, and an approximate 11.5 ton machine weight.

Q03How should the 50, 60, or 70 mm plunger package be selected?

Compare complete shot weight and required intensification pressure together. The published 50, 60, and 70 mm packages increase aluminum capacity from 1.57 to 3.00 kg while listed intensification pressure decreases from 162 to 83 MPa. The largest plunger is therefore not automatically the safest process choice.

Q04How do I confirm whether 3,000 kN clamping force is enough?

Calculate the projected area of every cavity, runner, overflow, and pressure-exposed slide, multiply it by the documented cavity-pressure assumption, and apply the required operating margin. Check that result against 3,000 kN separately from shot weight, die fit, and maximum published casting area.

Q05When should I compare the DC238T, DC400T, or DC550T?

Compare the DC238T when it satisfies the same project with sufficient margin and a smaller footprint. Review the DC400T or DC550T when clamp demand, complete shot, die opening, platen area, die handling, automation, or maintenance clearance exceeds a documented DC300T boundary.

Q06What should a DC300T quotation and FAT plan confirm?

The quotation should identify the selected shot package, controls, hydraulic components, core-pull groups, die interfaces, furnace and dosing equipment, extraction and spraying automation, guarding, utilities, spares, documentation, packing, destination, and exclusions. The FAT plan should define safety checks, dry-cycle operation, pressure and speed verification, alarms, recipes, interfaces, and the evidence supplied with the machine.

DC300T technical and commercial inquiry

Send one project file, receive one defined review scope

The fastest useful response starts with the evidence required to evaluate clamp demand, shot package, die fit, process window, cell interfaces, factory conditions, and commercial boundaries together.

  • 01

    Casting and process Alloy, drawing, projected area, complete shot, cavities, pressure assumption, quality target.

  • 02

    Die and movement Dimensions, thickness, weight, mounting, opening, ejection, core pulls, cooling, vacuum.

  • 03

    Production cell Cycle, annual volume, shifts, furnace, ladler, sprayer, extractor, trim and inspection.

  • 04

    Factory and delivery Layout, access, voltage, utilities, safety, destination, documentation, FAT, training and spares.

Get a Quote WhatsApp