DC2000T / Heavy casting-cell control center

2000 Ton Aluminum Cold Chamber Die Casting Machine

The DC2000T is a 20,000 kN cold chamber platform for large aluminum and magnesium programs. Purchasing it is a cell-engineering decision: casting pressure, complete shot, die movement, thermal control, automation, building services, logistics, safety, data, and acceptance evidence must be controlled as one project.

Published DC2000T data reviewed August 10, 2026 by Cathy, Director. Approved drawings, configuration schedules, and the signed technical agreement govern the supplied machine.

PROJECT REFERENCECONTROLLED REVIEW
DC2000T 2000 ton aluminum cold chamber die casting machine industrial visualization with clean English model marking
Industrial visualization based on the published heavy-machine reference. Final geometry, shot end, guarding, controls, component makes, colors, options, automation, and supply boundary require written confirmation.
Clamping force20,000 kN
Tie-bar opening1,350 × 1,350 mm
Aluminum shot22–39 kg
Approx. mass130 t

Control station 01 / Fit decision

Approve the platform only when seven project signals agree

Use one controlled data set across process, tooling, automation, maintenance, plant engineering, quality, and purchasing. A higher tonnage label cannot compensate for an unresolved shot package, inaccessible die, incomplete utility plan, or untestable acceptance requirement.

01

Clamp calculation

Total cavities, runners, overflows, and pressure-exposed slides. Record alloy, projected area, cavity-pressure basis, quality risk, and operating margin before comparing the result with 20,000 kN.

CALCULATION
02

Complete-shot balance

Include net castings, runners, biscuit, overflows, and process allowance. Check the total against one exact plunger package while preserving required intensification pressure.

MASS BALANCE
03

Die and motion envelope

Verify 600–1,600 mm die thickness, overall size, weight, platen mounting, opening, ejection, slides, core pulls, hoses, vacuum, lifting, insertion, and removal.

INTERFACE DRAWING
04

Process and quality window

Define fill profile, velocity, pressure, metal and die temperatures, vacuum, spray, thermal balance, defect limits, inspection plan, traceability, and approved process capability evidence.

PROCESS BASIS
05

Automated-cell sequence

Time furnace, dosing, spraying, extraction, quench, trim, conveyors, inspection, scrap return, recovery, guarding, I/O handshakes, and manual intervention as one cycle.

SEQUENCE FILE
06

Factory readiness

Freeze transport, rigging, foundation, crane coverage, access, floor loading, power, cooling, air, exhaust, oil-temperature control, drainage, maintenance, and safety zones.

SITE RELEASE
07

Commercial and acceptance control

Normalize inclusions, exclusions, interfaces, documentation, spares, packing, Incoterm, installation, training, warranty, FAT, SAT, open actions, and change ownership.

SIGNED BASELINE

Control station 02 / Shot-end envelope

Capacity and pressure move in opposite directions

Published DC2000T data gives boundary ranges, not a complete set of paired shot packages. Do not infer intermediate values. Require the quotation to list aluminum and magnesium capacity, intensification pressure, casting area, sleeve dimensions, injection datum, and interfaces for every offered plunger diameter.

Selection rule

Choose the smallest confirmed package that clears complete shot while retaining the required pressure and documented process margin.

PRESSURE-LEDCAPACITY-LED
Plunger range
120–160 mm
Aluminum shot
22–39 kg
Magnesium shot
15.8–28 kg
Intensification
133–75 MPa
Casting area range
1,400–2,630 cm²

Control station 03 / Published specification console

DC2000T technical parameters

Use these values for model screening and RFQ preparation. Final design release requires supplier drawings, datums, tolerances, component schedules, utilities, foundation loads, interfaces, software scope, and acceptance conditions.

A

Clamping and ejection

Clamping force
20,000 kN
Clamping stroke
1,400 mm
Ejecting force
650 kN
Ejection stroke
300 mm
Die thickness
600–1,600 mm
B

Platen and die space

Platen size
2,150 × 2,150 mm
Tie-bar diameter
280 mm
Tie-bar spacing
1,350 × 1,350 mm
Injection position
−200 / −400 mm*
Plunger launch distance
450 mm
C

Injection system

Injection force
1,510 kN
Injection stroke
1,050 mm
Plunger diameter
120–160 mm
Slow-shot speed
0.1–1.4 m/s
Max. air-shot speed
≥7 m/s
D

Shot and pressure boundaries

Aluminum shot
22–39 kg
Magnesium shot
15.8–28 kg
Intensification pressure
133–75 MPa
Casting area
1,400–2,630 cm²
Maximum casting area
5,000 cm²
E

Shot-sleeve interface

Flange diameter
260 mm
Flange protrusion
30 mm
System pressure
16 MPa
Oil-tank capacity
2,800 L
Motor power
110 kW
F

Machine and plant envelope

Approx. machine mass
130 t
Machine length
12.7 m
Machine width
4.4 m
Machine height
4.4 m
Final installation space
Project-specific

*Published injection-position values require confirmation of sign convention, reference face, centerline, tolerance, and available positions on the approved machine drawing.

Published manufacturer reference: ShiMi DC2000T Standard Cold Chamber Die Casting Machine. Use this public record to cross-check the web summary; approved supplier drawings and the signed technical agreement govern the final configuration.

Control station 04 / Casting-cell orchestration

The machine is one station in a controlled production system

A 130 ton machine cannot be evaluated independently from molten-metal delivery, extraction, finishing, safety, data, and recovery. Freeze who supplies, integrates, programs, tests, documents, and supports every interface.

01

Metal

Furnace, transfer, temperature, treatment, dosing accuracy, fill confirmation, alarms, and safe recovery.

02

Die

Thermal control, spray, blow-off, vacuum, core pulls, sensing, movement, services, and changeover.

03

DC2000T

Clamp, shot profile, pressure, ejection, recipes, interlocks, traceability, diagnostics, and machine safety.

04

Handling

Extraction, quench, cooling, marking, conveyors, rejection, robot reach, payload, collision zones, and recovery.

05

Finish

Trim, deburr, inspection, leak test, data capture, packing, scrap segregation, and quality release.

Control station 05 / System close-ups

Review access and verification points before layout release

These cleaned reference views support early interface discussions. They do not replace final supplier drawings or approve a particular component make, guard, hose route, control package, option, or service clearance.

CELL / CLAMPDC2000T clamping enclosure, structural base, service panels, and machine controls without Chinese labels

Clamping enclosure and die-service corridor

Use this zone to freeze die entry, mounting, tie-bar clearance, moving and fixed-side services, ejection, core pulls, cooling, vacuum, guarding, access doors, lifting points, isolation, and the maintenance corridor. The 1,350 x 1,350 mm opening is only one boundary; the full die and movement envelope must be approved from drawings.

CELL / SHOTDC2000T injection cylinder, tie bars, accumulator vessels, gauges, valves, and service hoses without Chinese labels

Injection, accumulator, and pressure interface

Confirm the exact 120-160 mm shot-end offering, sleeve and plunger interfaces, injection datum, accumulator safe-discharge method, gauges, pressure and velocity measurement, inspection access, hydraulic component schedule, critical spares, and acceptance evidence before the production cell is released.

Control station 06 / 130-ton site release

Do not release the purchase order before the factory route is buildable

The published 12.7 × 4.4 × 4.4 m envelope describes the bare machine, not the installed cell. Request transport configuration, shipping weights, centers of gravity, lift points, anchor loads, reactions, utility loads, heat rejection, and maintenance clearances from the final build.

ROUTE

Transport and rigging

Survey port, road, gates, turning radii, floors, pits, overhead restrictions, unloading area, crane or gantry plan, lifting accessories, staging, and weather protection.

BASE

Foundation and anchoring

Approve geotechnical assumptions, slab and pit design, static and dynamic loads, anchor pattern, grouting, leveling, oil containment, drainage, vibration, and survey datums.

SPACE

Die and service movement

Reserve crane coverage, die truck route, platen access, shot-end removal, accumulator inspection, lubrication, electrical and hydraulic service, guarding, escape, and rescue zones.

UTILITY

Connected plant loads

Confirm voltage, frequency, available fault current, grounding, cooling-water quality and duty, compressed air, exhaust, oil cooling, network, lighting, ambient limits, and isolation points.

Control station 07 / Acceptance data room

Convert every promise into a measurable record

FAT proves the agreed machine and cell scope under stated factory conditions; SAT confirms installation, interfaces, safety, performance, and documentation at the buyer's site. Neither test should rely on undefined “normal operation.”

FAT / MACHINE

Build and function evidence

  • Configuration and component schedule
  • Dimensions, movements, pressures, speeds, temperatures
  • Alarms, interlocks, guarding, safe stops
  • Recipe, data, backup, restore, permissions
  • Leak, noise, cleanliness, documentation, punch list
FAT / PROCESS

Repeatability evidence

  • Defined alloy, die, shot package, test conditions
  • Cycle definition and sample size
  • Velocity and pressure traces
  • Quality checks and traceability records
  • Pass criteria, deviations, correction, retest
SAT / SITE

Installed-cell evidence

  • Foundation, utilities, alignment, safety validation
  • Peripheral handshakes and recovery
  • Production trial and capability basis
  • Training and maintenance demonstration
  • Final documents, spares, open-action closure

Control station 08 / Buyer FAQ

Answers for heavy-cell selection and execution

Use these answers for early screening. Put project calculations, drawings, owners, tolerances, interfaces, test conditions, and acceptance evidence into the controlled technical agreement.

01What projects should shortlist the DC2000T aluminum die casting machine?

The DC2000T is an initial candidate for large aluminum or magnesium projects whose calculated clamp demand, complete shot, required pressure, die envelope, movement, automation, and plant interfaces fit the published 20,000 kN platform. Nominal tonnage alone does not approve a casting, die, cycle, or factory layout.

02What are the principal DC2000T technical specifications?

Published data lists 20,000 kN clamping force, 1,400 mm clamping stroke, 650 kN ejecting force, 300 mm ejection stroke, 600-1,600 mm die thickness, 2,150 x 2,150 mm platens, 1,350 x 1,350 mm tie-bar spacing, 1,510 kN injection force, 1,050 mm injection stroke, 110 kW motor power, a 2,800 L oil tank, and approximate 130 ton machine weight.

03How should the DC2000T shot-end package be selected?

Published boundaries cover 120-160 mm plunger diameters, 22-39 kg aluminum shot, 15.8-28 kg magnesium shot, 133-75 MPa intensification pressure, and 1,400-2,630 cm2 casting area. Request the exact paired values for every offered diameter and approve complete shot and required pressure together; do not interpolate a purchase configuration from range endpoints.

04How do I check whether 20,000 kN clamping force is sufficient?

Total the pressure-exposed projected area of cavities, runners, overflows, and slides, multiply by the agreed cavity-pressure basis, and apply the documented operating margin. Compare that result with 20,000 kN separately from shot capacity, die fit, and the published 5,000 cm2 maximum casting area.

05What factory planning is required for a 130 ton DC2000T?

Approve the shipping split, route survey, unloading and rigging study, center of gravity, crane coverage, foundation, anchoring, floor loads, 12.7 x 4.4 x 4.4 m bare-machine envelope, die-change route, maintenance zones, utilities, cooling, exhaust, guarding, and every peripheral footprint from final supplier drawings.

06What should a comparable DC2000T quotation and acceptance plan contain?

Require the selected shot end, controls, hydraulics, core pulls, cooling and vacuum interfaces, furnace and automation ownership, safety scope, utilities, drawings, software backups, manuals, spares, packing, installation, training, warranty, exclusions, and change-control route. FAT and SAT must define test conditions, instruments, data, pass criteria, corrective actions, and retest responsibility.

DC2000T controlled project dossier

Send one evidence pack for one accountable cell proposal

A useful response should state model fit, the exact shot-end package, preliminary interfaces and layout, utility basis, acceptance path, commercial boundary, open assumptions, and the owner and due date of every next action.

01 / CASTING

Alloy, drawings, projected area, cavity-pressure basis, cavities, net weight, runners, biscuit, overflows, complete shot, fill profile, quality, inspection, and traceability.

02 / DIE

Dimensions, 600–1,600 mm fit, weight, mounting, opening, ejection, slides, core pulls, cooling, vacuum, lifting, storage, and changeover.

03 / CELL

Cycle definition, annual volume, shifts, OEE basis, furnace, dosing, spray, extraction, quench, trim, inspection, scrap, guarding, I/O, data, and recovery.

04 / FACTORY

Layout, route, foundation, crane, utilities, safety standard, destination, Incoterm, FAT, SAT, documents, installation, training, warranty, and spares.

Get a Quote WhatsApp