DC3000T / Flagship project release center

3000 Ton Aluminum Cold Chamber Die Casting Machine

The DC3000T is the largest cold chamber platform in this published range. Its 30,000 kN clamp, large die envelope, 35-60 kg aluminum shot boundary, and approximately 210 ton machine mass make selection a capital-project decision—not a tonnage purchase.

Published DC3000T data reviewed August 10, 2026 by Cathy, Director. Approved calculations, drawings, schedules, acceptance plans, and the signed technical agreement govern the final configuration.

PROJECT CLASSULTRA-HEAVY / 30 MN
DC3000T 3000 ton aluminum cold chamber die casting machine visualization with clean English model marking
Clean industrial visualization based on the published ultra-heavy machine geometry. Confirm final structure, controls, component makes, shot end, guarding, options, automation, colors, and supply scope in writing.
Clamp30,000 kN
Die opening1,650 × 1,650 mm
Al shot listing35-60 kg
Machine massApprox. 210 t

Release gate 01 / Model justification

Five approvals decide whether the flagship platform is warranted

Each gate needs a named owner, controlled input revision, calculation or drawing, review date, approval status, open actions, and closure evidence. A larger nameplate cannot compensate for missing engineering.

  1. G1

    Casting physics

    Approve alloy, projected area, cavity-pressure basis, cavities, complete shot, fill profile, thermal balance, quality risks, inspection, traceability, and process margin.

    Decision: clamp + shot
  2. G2

    Die system

    Approve envelope, 850-2,000 mm thickness, weight, mounting, opening, ejection, slides, cores, cooling, vacuum, lifting, insertion, storage, and maintenance movement.

    Decision: fit + movement
  3. G3

    Production cell

    Freeze furnace, metal delivery, spray, extraction, quench, trim, inspection, conveyors, scrap, guarding, interfaces, recipes, data, fault states, and safe recovery.

    Decision: sequence + output
  4. G4

    Factory readiness

    Release route, rigging, foundation, anchors, floor, crane, power, cooling, air, exhaust, network, oil containment, access, maintenance zones, and installed footprint.

    Decision: site + utilities
  5. G5

    Contract evidence

    Normalize configuration, inclusions, exclusions, documents, software, spares, packing, installation, training, warranty, FAT, SAT, punch lists, retest, and change control.

    Decision: scope + acceptance

Release gate 02 / Shot-end selection

Ranges describe a boundary—not a purchasable package

The manufacturer lists 140-180 mm plungers across a capacity-pressure envelope. Request an exact row for every offered diameter, including metal capacity, intensification pressure, casting area, sleeve and flange geometry, injection datum, velocity basis, interfaces, instruments, and acceptance method.

Selection rule

Choose the smallest confirmed shot end that clears complete shot while preserving the required pressure and agreed process margin. Do not mix the highest capacity with the highest pressure.

PRESSURE PRIORITYCAPACITY PRIORITY
Plunger diameter
140-180 mm
Aluminum shot
35-60 kg
Magnesium shot
25.2-43.2 kg
Intensification pressure
125-75 MPa
Published casting area
2,360-3,920 cm²

Release gate 03 / Published technical baseline

DC3000T specifications

Use these values for initial model screening and RFQ preparation. The supplier must confirm exact datums, tolerances, shot package, utilities, foundation reactions, component schedules, control functions, drawings, and acceptance conditions before order release.

01

Clamping and ejection

Clamping force
30,000 kN
Clamping stroke
1,500 mm
Ejecting force
900 kN
Ejection stroke
300 mm
Die thickness
850-2,000 mm
02

Platen and die interface

Platen size
2,620 × 2,620 mm
Tie-bar diameter
340 mm
Tie-bar spacing
1,650 × 1,650 mm
Injection position
-250 / -450 mm*
Plunger launch distance
480 mm
03

Injection system

Injection force
1,950 kN
Injection stroke
1,150 mm
Plunger diameter
140-180 mm
Slow-shot speed
0.1-1.4 m/s
Maximum air-shot speed
≥7 m/s
04

Shot and pressure

Aluminum shot
35-60 kg
Magnesium shot
25.2-43.2 kg
Intensification pressure
125-75 MPa
Casting area
2,360-3,920 cm²
Maximum casting area
7,500 cm²
05

Hydraulic and power

Shot-chamber flange
280 mm
Flange protrusion
30 mm
System pressure
16 MPa
Oil-tank capacity
3,200 L
Motor power
150 kW
06

Factory planning

Approx. machine mass
210 t
Machine length
15 m
Machine width
4.8 m
Machine height
4.6 m
Installed cell envelope
Project-specific

*Confirm injection-position sign convention, reference face, centerline, tolerance, available positions, and shot-sleeve interface on the approved general-arrangement drawing.

Published manufacturer reference: ShiMi DC3000T Standard Cold Chamber Die Casting Machine. Use this public record to cross-check the web summary; approved supplier drawings and the signed technical agreement govern the final configuration.

Release gate 04 / Die and handling

The die must pass a movement study—not just a size check

At this scale, static fit is the first line of the review. Model the complete die, services, approach paths, collision zones, lifting operations, maintenance removal, and recovery positions in the coordinated cell layout.

STATIC

Envelope and interfaces

Overall width and height, 850-2,000 mm thickness, platen contact, tie-bar clearance, mounting, shot sleeve, ejector, core pulls, manifolds, connectors, sensors, cooling, vacuum, and guarding.

DYNAMIC

Every production movement

Opening, ejection, slides, cores, robot reach, spray path, extraction, part orientation, hose flex, collision zones, manual mode, fault position, and safe recovery sequence.

HANDLING

Mass, route, and changeover

Fixed and moving-half mass, center of gravity, lift points, crane capacity and coverage, die cart, insertion alignment, preheat, storage, transfer, change time, and rigging accessories.

SERVICE

Thermal and quality circuits

Heating and cooling maps, flow, pressure and temperature control, vacuum, venting, lubrication, spray recipe, filtration, leak detection, monitoring, traceability, and maintenance isolation.

Release gate 05 / Inspection windows

Freeze access before foundations and peripherals are released

These cleaned reference views support interface discussion only. They do not approve a component make, machine geometry, shot package, guard, option, hose route, color, or maintenance clearance.

GATE / CLAMPDC3000T clamping enclosure, structural base, service panels, and die-side access without Chinese labels

Clamping enclosure and die-service boundary

Use this view to review the 1,650 x 1,650 mm tie-bar opening, 850-2,000 mm die range, platen mounting, die insertion, fixed and moving-side utilities, ejection, core pulls, cooling, vacuum, guarding, isolation, lifting, and service corridors. Only approved interface and foundation drawings release the installation.

GATE / SHOTDC3000T injection cylinder, tie bars, accumulator vessels, valves, gauges, and service structure without Chinese labels

Injection, accumulator, and pressure-service boundary

Freeze the offered 140-180 mm shot package, sleeve and flange interface, injection-position datum, safe accumulator discharge, calibration points, pressure and velocity records, inspection access, hydraulic component schedule, oil and filtration requirements, critical spares, and FAT/SAT measurement method.

Release gate 06 / 210-ton site readiness

The bare-machine footprint is not the installed production cell

The published 15 × 4.8 × 4.6 m envelope excludes shipment splits, working clearances, platforms, peripherals, die movement, crane coverage, maintenance routes, guarding, utilities, and safe escape. Coordinate the site from approved drawings.

01 / ROUTE

Transport feasibility

Survey port, road, permits, axle and bridge limits, gates, turning radii, floors, pits, overhead restrictions, unloading position, staging, weather protection, and recovery contingencies.

Release: signed route report
02 / LIFT

Rigging and assembly

Define shipping splits, weights, centers of gravity, lift points, crane or gantry, spreaders, shackles, tailing, exclusion zones, temporary works, supervision, and assembly sequence.

Release: approved lift study
03 / BASE

Foundation and anchoring

Approve geotechnical and slab assumptions, pits, static and dynamic reactions, anchors, grout, leveling, alignment datums, vibration, containment, drainage, and as-built survey.

Release: civil drawing pack
04 / PLANT

Utilities and service access

Freeze voltage, frequency, fault current, grounding, cooling-water duty and quality, air, exhaust, oil cooling, network, lighting, ambient limits, isolation, crane and maintenance zones.

Release: coordinated utility plan

Release gate 07 / Contract and acceptance

Pay for a measurable result and a usable technical handover

Every offer should identify the supplied configuration, interface owner, document, test method, evidence, exclusion, and closure route. Normalize these items before comparing price or delivery.

CONFIGURATION

One controlled baseline

Machine, exact shot end, controls, hydraulics, core pulls, cooling, vacuum, safety, furnace, dosing, spray, extraction, finishing, data, options, approved makes, and exclusions.

DOCUMENTS

Information that operates the cell

General arrangement, foundation, utilities, interfaces, electrical and hydraulic drawings, manuals, software backups, passwords, certificates, parts lists, maintenance plans, and training records.

FAT

Evidence before shipment

Define build inspection, movements, functions, pressure and velocity traces, alarms, guarding, recipes, data, test conditions, samples, quality checks, pass criteria, punch lists, and retest.

SAT

Evidence at the installed site

Verify foundation, utilities, alignment, peripheral handshakes, safety, fault recovery, production trial, capability basis, training, documents, spares, open actions, and final release.

Release gate 08 / Procurement FAQ

Direct answers for the flagship project team

Use these answers for early screening, then put project calculations, drawings, responsibilities, interfaces, tolerances, test conditions, evidence, and change control into the signed technical agreement.

G8.1What projects should shortlist the DC3000T aluminum die casting machine?

The DC3000T is an initial candidate for ultra-large aluminum or magnesium programs whose documented clamp demand, complete shot, pressure, die envelope, movement, automation, and factory interfaces fit the published 30,000 kN platform. The 3,000 ton label alone does not approve the casting, die, cycle, quality plan, or capital project.

G8.2What are the principal DC3000T technical specifications?

Published data lists 30,000 kN clamping force, 1,500 mm clamping stroke, 900 kN ejecting force, 300 mm ejection stroke, 850-2,000 mm die thickness, 2,620 x 2,620 mm platens, 1,650 x 1,650 mm tie-bar spacing, 1,950 kN injection force, 1,150 mm injection stroke, 150 kW motor power, a 3,200 L oil tank, and approximate 210 ton machine weight.

G8.3How should the DC3000T shot-end package be selected?

Published boundaries cover 140-180 mm plunger diameters, 35-60 kg aluminum shot, 25.2-43.2 kg magnesium shot, 125-75 MPa intensification pressure, and 2,360-3,920 cm2 casting area. Obtain exact paired values for each offered diameter and approve complete shot and required pressure together; do not construct a purchase configuration by mixing range endpoints.

G8.4How do I check whether 30,000 kN clamping force is sufficient?

Total the pressure-exposed projected area of every cavity, runner, overflow, and slide, multiply by the agreed cavity-pressure basis, then apply the documented operating margin. Compare that result with 30,000 kN separately from shot capacity, die fit, movement, and the published 7,500 cm2 maximum casting area.

G8.5What factory planning is required for a 210 ton DC3000T?

Approve shipping splits, route survey, permits, unloading and lift studies, centers of gravity, crane or gantry coverage, foundation reactions, anchors, floor capacity, the 15 x 4.8 x 4.6 m bare-machine envelope, die and service routes, utilities, cooling duty, exhaust, guarding, oil containment, and all peripheral footprints from final drawings.

G8.6What should the DC3000T FAT, SAT, and commercial scope define?

Require the selected shot end, controls, hydraulics, core pulls, cooling and vacuum interfaces, furnace and automation ownership, safety scope, utilities, drawings, software, manuals, spares, packing, installation, training, warranty, exclusions, and change control. FAT and SAT must state conditions, instruments, samples, data, pass criteria, corrective actions, and retest responsibility.

DC3000T release-package request

Send the project evidence needed for a gate decision

A useful reply should state whether the DC3000T is justified, identify the exact shot end, define preliminary cell and site interfaces, normalize the commercial scope, establish the acceptance route, and assign every unresolved assumption to an owner and date.

  1. 01 / CASTING

    Alloy, drawings, projected area, cavity-pressure basis, cavities, net weight, runners, biscuit, overflows, complete shot, fill, thermal balance, quality, inspection, and traceability.

  2. 02 / DIE

    Size, 850-2,000 mm thickness, mass, mounting, opening, ejection, slides, cores, cooling, vacuum, lifting, insertion, storage, changeover, and maintenance movements.

  3. 03 / CELL

    Cycle, volume, shifts, OEE basis, furnace, metal delivery, spray, extraction, cooling, trim, inspection, scrap, guarding, I/O, data, faults, and recovery.

  4. 04 / FACTORY

    Layout, route, rigging, floor, foundation, crane, utilities, safety, destination, Incoterm, FAT, SAT, documents, installation, training, warranty, and spares.

Get a Quote WhatsApp